WASHING MACHINE MAINTENANCE
Sycamore Rejuvenation Project
LANDSCAPE UPDATE
PROGRESS REPORTS
- Management typically schedules 10 residential buildings per year for painting and insulation, but due to COVID, this work began late in the year. Ms. Giles projected that six buildings - 90, 3, 15, 33, 34, and 58 - would be completed or nearly complete by year’s end.
- The garage restoration and painting project for courts 6,8, and 14 began on September 7 and was on track to conclude in early December. Each garage received a power wash, carpentry repairs, termite treatment, fumigation, and finish painting.
- Annual garage inspections also took place this autumn.